The implementation of task no. 3 entitled: „Construction of the City Park in Pobiedziska” for the amount of PLN 2,807,598.55 gross, with a completion deadline of 129 days from the date of signing the contract, i.e., December 29, 2023, is ongoing.
Cleanup works and part of the earthworks have been completed, a technological channel has been built, the fence has been dismantled, bollards have been embedded, and constructions for paths have been made. The area has been prepared for greenery landscaping.
The value of the work completed so far amounts to PLN 1,475,447.59.